SAN NICOLA STADIUM: A project that is 33 years old

1990 LAVORI STADIO SAN NICOLA - BARI

June, 1990.

Bari, San Nicola Stadium: a daydream for the people of Bari and for the young Primiceri, who was commissioned to do the great job.

On the occasion of the World Cup, Fifa decided to entrust the organization of the immense event to Italy. For the city of Bari this was a reason for modernization and work soon began on the Astronave, the third largest stadium in Italy, built by the archistar Renzo Piano.
Primiceri was commissioned with the ambitious task of creating all the equipment for the electrical system and all the transformation substations, the beating heart of the functioning of the San Nicola.

From this moment, the choice and the need to expand our company: a new large industrial plant was built in the Industrial Zone of Bari.

The rest is history.

MOVYON: a new job for the Group Autostrade Per l’Italia

MOVYON: a new job for the Group Autostrade Per l'Italia

Quadri d’Autore of the PRIMICERI Group is proud to announce the supply of the new ‘Quadri pista 2.0’ for motorway toll booths. This is an order requested by MOVYON – a company of the Autostrade per l’Italia Group.

Primiceri S.p.A. believes a lot in technological innovation and has developed a latest generation solution for MOVYON that meets markets demands.

Thanks to this solution, the speed and efficiency of the management of toll stations and lanes used for the Telepass service has improved.

This is an important milestone achieved together with the Autostrade per l’Italia Group!

We are deeply committed to improving our country’s infrastructure.

 

MEXICO: A new container in Dos Bocas

Container Dos Bocas. A new project in Mexico

Primiceri is pleased to inform you that an important supply for the foreign market has been successfully completed: DOS BOCAS (Mexico).
The project was aimed at the construction of an electrical room for the electrical generator of a steam turbine for our Customer Baker Hughes, final customer TECHNT for PEMEX.
The scope of the supply in detail consists of an electrical room measuring 15 m x 3.9 m x 4 m (H) and weighing 48,000 kg to which is attached a battery room measuring 4 m x 3.9 m x 4 m ( H) and weight 13.000 Kg.
The project is characterized by various certifications including UL, ANSI and NEMA and it took about 14 months to complete it.
We are proud to have completed this project which confirms us as leading suppliers in the international Oil & Gas sector.

Let’s look here to discover our foreign projects made in America: https://bit.ly/Container_in_Arizona

Visit our social media pages on LinkedIn: https://www.linkedin.com/company/primicerispa/

PRIMICERI, A new MCC in America

MOTOR CONTROL CENTER (MCC) – UL845

2023

Plant location

OFFSHORE – INTERNATIONAL SEA (U.S.A)

Company

NFE FAST LNG – LNTP 

Contractor

BAKER HUGHES for NEW FORTRESS ENERGY